Denver Colorado (CO) Construction Lien Attorneys
Colorado Mechanic’s
Lien Claims – Overview For Prospective
Clients
If you need construction lien lawyers to represent you in a mechanic's lien claim you can trust the services of HHMR, who has expertly aided Colorado companies as construction lien attorneys in all aspects of contractor claims. A construction dispute lawyer becomes necessary in a construction lien claim to guide you through the complicated payment claims and the demanding and precise process involved.
Colorado mechanic’s lien
claims require strict compliance with
C.R.S. § 38-22-101, et seq. and any
failure to meet the requirements of the
statute will potentially defeat the lien
claim. The first requirement is that the
Notice of Intent to Claim a Lien claim
form be properly completed, signed,
notarized, and served personally by
certified mail or personal delivery on
both the owner of the property and the
general contractor of the project within
four months of the last work performed
on the project (or within four months of
providing materials in the case of a
supplier).
The Notice of Intent to Claim a Lien
claim form should be completed in
detail, referencing the legal
description and address of the property,
the contract for which payment is
sought, and the precise amount of the
lien amount claimed. Mistakes or
omissions in address, legal description,
the basis for the claim, signatures,
notaries, and/or the exact amount owed
on the claim can all become issues that
jeopardize the claim. It is best to have
a knowledgeable attorney review the
completed form for technical compliance
before serving it by mail or in person
on the general contractor and owner. It
is also important to verify the current
name, registered agent for service, and
address of the legal owner of the
property before sending the Notice of
Intent to Claim a Lien.
Formal service of the Notice of Intent
to Claim a Lien on both the owner and
general contractor must be completed
within the four months following the
last substantial work on the project.
“Substantial work” does not usually
involve punch list work, warranty work,
removal of equipment, or cleanup. For
this reason it is the best practice to
file the Notice of Intent to Claim a
Lien within sixty days after the last
substantial work was done, in order to
make sure that time requirements are
easily satisfied without creating
potential procedural compliance issues.
After the Notice of Intent to Claim a
Lien is served on both the property
owner and the general contractor, the
claiming party must wait for at least
ten days before recording the notice in
the land records for the county in which
the property is located. Once again,
this recording process must be completed
within the four months after the last
substantial work on the project by the
subcontractor/material supplier. If the
lienable property is located in multiple
counties, the recording should take
place in all counties where the land is
located. Care must be taken not to
record the lien claim notices before the
expiration of the ten day period
provided in the statute. During this
ten-day time period it is good practice
to directly contact the parties served
with the notice to attempt resolution of
the claims. Once the notice has been
recorded, it serves as public notice of
the pending claim.
Within six months of the date of the
last substantial work on the project,
the party claiming the mechanic’s lien
under the previously-sent notice must
file a lawsuit to foreclose the lien and
seek formal determination of the lien’s
validity, compliance with procedure, and
amount. A Notice of Lis Pendens also
should be filed in the land records when
the mechanic’s lien foreclosure suit is
filed. The foreclosure process is
required to be handled by an attorney if
the lien claimant is a corporation or
similar business entity. It is once
again important to use the services of a
knowledgeable attorney with prior
experience in handling mechanic’s lien
claim actions in the foreclosure stage
of the lien claim process.
The lien bears interest at the rate of
12% simple interest, and it is possible
to obtain an award of court costs and
interest. It is unusual to be awarded
attorney’s fees, unless the claim is
made under the Mechanic’s Lien Trust
Fund provisions of the statute
(discussed below).
Construction Lien Lawyers, Construction Claims Attorney, Construction Dispute Lawyer, Mechanic's Lien Claim, Notice Liens, Non Payment Liens, Payment Claims and More
All mechanic’s lien claimants will
typically be joined in the same
foreclosure proceeding, and it is
important to bring all potential or
actual lien claimants into the case.
While this may result in increased court
costs, these costs are generally
recoverable in the final order of
judgment in the case. The principal
challenge for most mechanic’s lien
claimants is the priority of a
commercial lender’s deed of trust on the
subject property, and whether it will be
senior (i.e., have a higher priority)
than the mechanic’s liens against the
property. The date of the deed of trust
typically decides this question.
All mechanic’s lien claims are given the
same lien priority date, and it will be
the first date that any mechanic’s lien
claimant performed any work on the
subject property that could give rise to
a lien claim. Thus, even if a mechanic’s
lien claimant did not perform early work
on a project, that claimant’s work will
be assigned a uniform priority date
identical to the earliest work done by
the mechanic’s lien claimant that
performed the earliest work.
The Colorado Mechanic’s Lien Trust
Fund Statute
The Colorado Mechanic’s Lien Trust Fund
Statute, C.R.S § 38-22-127, is a
provision of the Colorado mechanic’s
lien statute that presents both special
problems for general contractors and
special opportunities for subcontractors
and material suppliers. It provides
requirements that when general
contractors are paid for the work of
subcontractors or for the materials
supplied by others, that the general
contractor is required to hold the money
“in trust” for the subcontractor or
supplier. Any failure to pay money that
is owed to the subcontractor or supplier
under this “trust” requirement will
create potential liability to the
subcontractor or supplier on the part of
the general contractor for up to triple
damages and attorney’s fees for
intentional non-payment to the
subcontractor or supplier.
Additional information on this subject
can be obtained by clicking on the link
to an article written by HHMR that
appeared in the January/February 2008
issue of The Colorado Builder Forum.
http://www.hhmrlaw.com/publications/Builders_Forum.pdf
The applicability of the Colorado
Mechanic’s Trust Fund Statute to a
particular case is very fact-specific,
and should be discussed with a
knowledgeable attorney to determine
whether the provisions of the statute
apply. Most importantly, it is not
necessary for the unpaid party to comply
with the (four and six month) time
provisions of the statute, if the lien
claim has been lost due to procedural
non-compliance or the passage of time.
The firm has the knowledge and experience to provide assistance to construction-related businesses with a construction lien claim, a non payment lien, payment claims, and all related matters. Please contact David M. McLain or Buck Mann if you have matters that you would like to discuss concerning Colorado mechanic's lien claims.
HHMR has earned a long list of satisfied clients by providing a construction defects lawyer, construction defect attorney, or a construction claims attorney that fought for their rights. They can sort through disputed claims and explain the complicated process associated with a mechanic's lien or other contractor claims. You can count of HHMR to represent you as construction lien lawyers in a mechanic's lien claim, as they are reputable construction lien attorneys in Denver CO 80206 and throughout the state of Colorado.
ADDITIONAL PRACTICE AREAS
Higgins, Hopkins, McLain & Roswell are Construction Defect Litigation Attorneys. Our main offerings include: Construction Disputes and Construction Lien Claims defense for developers, builders, subcontractors, design professionals, insurers and more.
Contact Form
Common Tags:
Construction Lien Attorneys, Construction Lien Lawyers, Mechanic's Lien Claim, Construction Lien Claim Lawyers, Claim Of Mechanic's Lien Attorneys, Payment Claims Lawyers, Non Payment Lien Attorneys, Dispute Claims, Notice Lien Lawyers, Contractor Claims Attorneys, Construction Defects Lawyer, Construction Defect Attorney, Construction Dispute Lawyer, Construction Claims Attorney, Construction Claims Lawyer
We serve the following Colorado Locations:
Denver CO 80206, Denver County, Jefferson County, Arapahoe County, Douglas County, Adams County
© 2009 Higgins, Hopkins, McLain &
Roswell, LLC
Use of this website is subject to:
TERMS OF USE
Website Development and Maintenance
by:
